East African Crude Oil Pipeline

The East African Crude Oil Pipeline (EACOP) has reached 79% completion, with construction works in Tanzania advancing toward completion by July 2026. The project is expected to transport up to 246,000 barrels of oil per day and has created 12,000 jobs in Tanzania and Uganda.

Ndejembi made the statement during a press briefing held in Dar es Salaam on January 05, 2025, following an inspection visit by Uganda’s Minister of Energy and Mineral Development, Dr. Ruth Nankabirwa, to the Chongoleani section of the pipeline project in Tanga Region. The visit aimed to review progress on the Tanzanian segment of the crude oil pipeline linking Hoima in Uganda to Chongoleani in Tanzania.

According to Ndejembi, the project is expected to be completed in July 2026 and will have the capacity to transport 246,000 barrels of crude oil per day once construction is finalised. Ndejembi also said that a total of 12,000 jobs have been created for citizens of Tanzania and Uganda during the implementation of the project, involving youth and local communities in construction and related activities. For her part, Uganda’s Minister of Energy and Mineral Development, Dr. Ruth Nankabirwa, thanked the President of Tanzania, Dr. Samia Suluhu Hassan, for her commitment to implementing the project, stressing that it has brought economic transformation to East African countries.

Read more at: https://www.tanzaniainvest.com/energy/eacop-construction-update-january-2026

epbtz

About Author

You may also like

Business

Tanzania Concludes Wigu Hill Rare Earth Project Litigation with Final Payment

Tanzania has completed its US$27 million settlement with Montero over the expropriation of the Wigu Hill rare earth project. With
Business

EAC Unveils $12.5M ENSURE Project to Transform East African Agriculture and Impact 5 Million Lives

There are many variations of passages of Lorem Ipsum available but the majority have suffered alteration in that some injected